Scope, Schedule & Cost Management Mastery
Duration: 8 Hours | Focus: Three Critical Knowledge Areas
| Time | Session | Topics | Key Deliverables |
|---|---|---|---|
| 9:00-10:30 AM | Session 1 | Project Scope Management | WBS Creation, Requirements Matrix |
| 10:45-12:15 PM | Session 2 | Project Schedule Management | Network Diagrams, CPM Analysis |
| 1:15-2:45 PM | Session 3 | Project Cost Management | Cost Estimates, Budget Baseline |
| 3:00-4:30 PM | Session 4 | Earned Value Management | EVM Calculations, Forecasting |
| 4:45-6:00 PM | Session 5 | Practice & Review | Sample Questions, Action Plans |
S.S.C. = Success Strategy for Certification
Project Scope Management ensures that the project includes all and only the work required to complete the project successfully. It's about defining what's IN and what's OUT.
Purpose: Creates a scope management plan that documents how the project and product scope will be defined, validated, and controlled.
Situation: You're managing a new mobile app development project. The client wants to start coding immediately without proper scope planning.
Action: Explain that Plan Scope Management must come first to establish how requirements will be gathered, scope will be defined, and changes will be controlled.
Result: Prevents scope creep and ensures all stakeholders understand the scope management approach.
Purpose: Determines, documents, and manages stakeholder needs and requirements to meet project objectives.
| Requirement Type | Description | Example |
|---|---|---|
| Business Requirements | Higher-level needs of the organization | Increase customer satisfaction by 20% |
| Stakeholder Requirements | Needs of stakeholder groups | Users need single sign-on capability |
| Solution Requirements | Features and functions of the product | System must process 1000 transactions/minute |
| Functional Requirements | What the product must do | Calculate taxes automatically |
| Non-functional Requirements | Performance, security, usability | 99.9% uptime availability |
| Transition Requirements | Temporary capabilities for transition | Data migration from legacy system |
| Project Requirements | Actions, processes for project | Monthly status reports required |
| Quality Requirements | Conditions for validation | Zero critical defects in production |
One-on-one conversations with stakeholders. Best for sensitive topics and detailed exploration.
Moderated discussions with prequalified stakeholders. Great for gathering diverse perspectives.
Cross-functional sessions for rapid requirement definition. Effective for complex projects.
Group creativity technique for generating ideas. Encourages innovative thinking.
Structured brainstorming with voting. Reduces bias and groupthink.
Anonymous expert consensus building. Useful when experts can't meet in person.
Visual representation of requirements relationships. Helps identify connections.
Grouping related requirements. Useful for organizing large numbers of requirements.
Structured data collection from large groups. Cost-effective for broad input.
Job shadowing and workflow analysis. Reveals actual vs. stated requirements.
Working models for feedback. Clarifies requirements early in the project.
Comparing practices against industry standards. Identifies best practices and gaps.
Project: Building a new e-commerce platform for a retail company
Requirements Gathering Approach:
Purpose: Analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model.
Network Diagram:
| Technique | Description | Impact on Cost | Impact on Risk | When to Use |
|---|---|---|---|---|
| Crashing | Adding resources to critical path activities | Increases | Minimal increase | Budget available, resources can be added |
| Fast Tracking | Performing activities in parallel | Minimal increase | Significantly increases | Activities can overlap, risk acceptable |
Situation: Your software development project is 2 weeks behind schedule due to complexity in the database design phase. The client needs the product launched on the original date for a trade show.
Crashing Analysis:
| Activity | Normal Duration | Crash Duration | Cost to Crash | Cost per Day |
|---|---|---|---|---|
| Frontend Development | 10 days | 7 days | $9,000 | $3,000 |
| Backend Development | 12 days | 9 days | $6,000 | $2,000 |
| Testing | 8 days | 6 days | $4,000 | $2,000 |
Decision: Crash Backend Development and Testing first (lowest cost per day), then Frontend if more compression needed.
Fast Tracking Option: Start testing activities in parallel with development completion, but increases risk of rework.
| Aspect | Resource Leveling | Resource Smoothing |
|---|---|---|
| Project Duration | May extend | Does not extend |
| Critical Path | May change | Unchanged |
| Resource Usage | Optimizes throughout project | Limited to available float |
| Primary Goal | Resolve resource conflicts | Optimize resource usage |
Purpose: Monitoring the status of project activities to update project schedule and managing changes to the schedule baseline.
| Metric | Positive Value | Negative Value | Index > 1.0 | Index < 1.0 |
|---|---|---|---|---|
| Schedule Variance | Ahead of schedule | Behind schedule | N/A | N/A |
| Schedule Performance Index | N/A | N/A | Ahead of schedule | Behind schedule |
Question: An activity has an optimistic duration of 4 days, most likely of 6 days, and pessimistic of 14 days. What is the expected duration using PERT?
Project Cost Management includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so that the project can be completed within the approved budget.
Purpose: Establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs.
| Cost Type | Description | Example | Project Impact |
|---|---|---|---|
| Direct Costs | Directly attributable to project work | Team salaries, equipment, materials | Fully controllable by PM |
| Indirect Costs | Overhead costs shared across projects | Utilities, admin support, facilities | Allocated to project |
| Fixed Costs | Do not change with project activity level | Insurance, rent, license fees | Predictable expense |
| Variable Costs | Change with amount of work performed | Materials, contractor hours | Scales with project size |
| Sunk Costs | Money already spent and cannot be recovered | Research completed, equipment purchased | Should not influence future decisions |
| Opportunity Costs | Value of best alternative given up | Choosing Project A over Project B | Consider in project selection |
Purpose: Developing an approximation of the monetary resources needed to complete project activities.
| Technique | Accuracy | Cost to Prepare | When to Use | Typical Range |
|---|---|---|---|---|
| Analogous (Top-down) | Low | Low | Early in project, limited information | -25% to +75% |
| Parametric | Medium to High | Medium | When statistical relationships exist | -15% to +25% |
| Bottom-up | High | High | When detailed WBS available | -5% to +10% |
| Three-Point | High | Medium | When uncertainty exists | -10% to +15% |
Analogous Estimating:
Parametric Estimating:
Bottom-up Estimating:
| Cost Category | Description | Examples | Impact |
|---|---|---|---|
| Prevention Costs | Costs to prevent defects | Training, processes, quality planning | Investment upfront saves money later |
| Appraisal Costs | Costs to assess quality | Inspections, testing, reviews | Find defects before customer |
| Internal Failure Costs | Defects found before delivery | Rework, scrap, debugging | Costly but contained internally |
| External Failure Costs | Defects found after delivery | Warranty work, returns, lawsuits | Most expensive, damages reputation |
PAIL Bucket: Prevention, Appraisal, Internal failure, Loss (external failure)
Cost Order: Prevention < Appraisal < Internal Failure < External Failure
Purpose: Aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.
| Component | Purpose | Who Controls | When Used |
|---|---|---|---|
| Work Package Estimates | Cost for specific deliverables | Project Manager | Ongoing project execution |
| Contingency Reserves | Known risks (known unknowns) | Project Manager | When identified risks occur |
| Management Reserves | Unknown risks (unknown unknowns) | Senior Management | Unplanned scope changes |
Purpose: Monitoring the status of the project to update the project costs and managing changes to the cost baseline.
| Metric | Positive Value | Negative Value | Index > 1.0 | Index < 1.0 |
|---|---|---|---|---|
| Cost Variance | Under budget | Over budget | N/A | N/A |
| Cost Performance Index | N/A | N/A | Under budget | Over budget |
Situation: Your project is 6 months into a 12-month timeline. Current project status:
Analysis:
Interpretation: Project is over budget and behind schedule. Need corrective action for both cost and schedule performance.
Question: A project has EV = $50,000 and AC = $60,000. What is the Cost Performance Index (CPI) and what does it indicate?
EVM is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress.
| Measurement | Symbol | Definition | What It Represents |
|---|---|---|---|
| Planned Value | PV | Authorized budget assigned to scheduled work | How much work should be done |
| Earned Value | EV | Measure of work performed in budget terms | How much work is actually done |
| Actual Cost | AC | Realized cost incurred for work performed | How much the completed work actually cost |
| Budget at Completion | BAC | Total planned budget for the project | Total planned project cost |
| Index | Good Performance | Poor Performance | Perfect Performance | Interpretation |
|---|---|---|---|---|
| CPI | > 1.0 | < 1.0 | = 1.0 | Cost efficiency: value earned per dollar spent |
| SPI | > 1.0 | < 1.0 | = 1.0 | Schedule efficiency: progress rate vs. plan |
| Variance | Positive Value | Negative Value | Zero Value | Key Insight |
|---|---|---|---|---|
| CV | Under budget | Over budget | On budget | Cost performance vs. baseline |
| SV | Ahead of schedule | Behind schedule | On schedule | Schedule performance vs. plan |
Project Status at Month 8 of 12-month project:
Variance Analysis:
Performance Indices:
Forecasting (Typical Performance):
Interpretation:
Situation: You're managing a software development project with poor performance metrics:
Available Corrective Actions:
| Action | Impact on Cost | Impact on Schedule | Risk Level | Feasibility |
|---|---|---|---|---|
| Add senior developers | Increases AC | Improves SPI | Low | High if available |
| Reduce scope | Improves CPI | Improves SPI | Medium | Requires customer approval |
| Outsource components | May improve CPI | May improve SPI | High | Depends on vendor capability |
| Fast track activities | Minimal impact | Improves SPI | High | High but risky |
Recommended Approach:
| Limitation | Description | Mitigation Strategy |
|---|---|---|
| Critical Path Blind | Doesn't show critical path status | Combine with CPM analysis |
| Quality Neutral | Doesn't measure quality of work | Include quality metrics separately |
| Baseline Dependent | Only as good as original estimates | Regular baseline reviews and updates |
| Late Project Paradox | SPI approaches 1.0 near project end | Focus on milestone completion dates |
| Overhead Burden | Requires significant data collection | Automate data collection where possible |
PV: What you PLANNED to spend
EV: What you EARNED (deserved)
AC: What you ACTUALLY spent
Positive CV/SV: Good news (under budget/ahead)
Negative CV/SV: Bad news (over budget/behind)
CPI > 1.0: Getting more than $1 value per $1 spent
SPI > 1.0: Going faster than planned
BAC ÷ CPI: Most common forecast formula
If CPI = 0.8: Project will cost 25% more
Question: A project has BAC = $100,000, EV = $40,000, AC = $50,000, and PV = $45,000. The project manager wants to know how much efficiency is needed on remaining work to complete within the original budget. What is the TCPI?
This session combines all Day 3 concepts through practical exercises, exam-style questions, and real-world scenarios.
Scenario: You're managing a corporate event planning project for a 500-person annual conference.
Challenge: Calculate the critical path for the following activities:
| Activity | Duration (days) | Predecessors | Description |
|---|---|---|---|
| A | 4 | - | Requirements Analysis |
| B | 6 | A | System Design |
| C | 3 | A | Database Design |
| D | 8 | B | Frontend Development |
| E | 7 | C | Backend Development |
| F | 4 | D, E | Integration Testing |
| G | 2 | F | Deployment |
Scenario: Mid-project health check for a mobile app development project
| Work Package | Planned Value | Earned Value | Actual Cost | % Complete |
|---|---|---|---|---|
| Requirements | $15,000 | $15,000 | $16,500 | 100% |
| UI Design | $20,000 | $18,000 | $19,200 | 90% |
| Backend Dev | $35,000 | $21,000 | $28,000 | 60% |
| Frontend Dev | $25,000 | $10,000 | $12,500 | 40% |
| Testing | $5,000 | $0 | $0 | 0% |
| TOTALS | $100,000 | $64,000 | $76,200 | - |
Current Situation Analysis:
Recommended Actions:
During project execution, the customer requests a significant change that would add new functionality. The change would increase project duration by 15% and cost by 20%. What should the project manager do FIRST?
A project manager needs to compress the schedule by 10 days. The following information is available about critical path activities:
| Activity | Normal Duration | Crash Duration | Crash Cost |
|---|---|---|---|
| A | 8 days | 6 days | $4,000 |
| B | 12 days | 8 days | $8,000 |
| C | 6 days | 4 days | $6,000 |
Which activity should be crashed FIRST?
A project has the following status: BAC = $200,000, EV = $80,000, AC = $100,000, PV = $90,000. If the current cost performance continues, what will be the final project cost?
A software project is experiencing the following: CPI = 0.92, SPI = 0.88, and the customer is requesting additional features. The project manager should be MOST concerned about:
| Timeline | Focus Areas | Activities | Success Metrics |
|---|---|---|---|
| Next 3 Days | Formula Memorization | Practice 50+ EVM problems daily | 95% accuracy on calculations |
| Week 1 | Process Integration | Create process flow diagrams | Explain all 18 processes |
| Week 2 | Scenario Practice | 100+ situational questions | 80% correct on first attempt |
| Week 3 | Mock Exams | Full-length practice tests | Consistent 70%+ scores |
| Week 4 | Final Review | Focus on weak areas | Ready for exam scheduling |
• WBS = 100% rule
• Validate = Customer acceptance
• Control = Prevent scope creep
• Critical Path = Zero float
• PERT = (O+4M+P)÷6
• Crash = Add resources
• CPI = EV ÷ AC
• EAC = BAC ÷ CPI
• TCPI = (BAC-EV)÷(BAC-AC)
• Index > 1.0 = Good
• Index < 1.0 = Bad
• Positive variance = Good
Tomorrow's Focus: Quality, Resources, Communications & Risk Management